Contracting confusion

Peter Solari LLB(Hons) FRICS FCIArb

 

is a Chartered Surveyor, a Chartered Arbitrator, and a partner of PSP Construction Consultants, and practises as both quantity surveyor and arbitrator.  He is a CIArb approved tutor and lecturer at the SE Branch associate-level entry courses.

 

Architects, surveyors and others engaged in the construction industry (at least those longer in the tooth) may well be rather confused. At least, if they are not confused they jolly well ought to be. Look at it this way:

 

Years ago there was a standard form of contract which was issued by the Joint Contracts Tribunal (JCT) and was  commonly known as JCT63. The majority of building contracts, large or small, were let on it. Architects and surveyors generally knew their way around it, clause by clause. It was a well tried contract, which through use and abuse largely survived and served all parties moderately well. The contract was long (but not too long) being about 17,000 words. Yes, there was litigation concerning certain clauses, which led to amendments being made; but generally the allocation of risk as between Employer and Contractor seemed fair, and we all felt there was a sureness as to the relationships between architect, surveyor and contractor and as to the day-to-day procedures adopted.

 

The reference to arbitration was contained in five paragraphs totalling about 500 words. One provision was that no arbitration shall be commenced until practical completion of the works was achieved.  Very sensible - let the building works get completed before the arguments start.

 

What has changed? Seemingly everything. In 1980 the JCT decided, partly because of the volume of amendments being published to JCT63, to issue an entirely new contract. So was born JCT80 (the successor of which is now JCT98) both of which are at least triple the size of the old contract, with annexes and appendices included for good measure

The reference to arbitration now incorporates by reference a whole set of separate rules (CIMAR). Adjudication clauses are of course also included.  There is no longer a provision that arbitration proceedings should await practical completion.

All parties were (and are) represented on the JCT, including consultants, employers contractors and subcontractors. The resultant new contract was inevitably going to be the lowest common denominator of agreement. In other words, a compromise.  Moreover a compromise which many would say re-allocates the risks to the detriment of the Employer. No matter.

 

Then we had the plethora of new subcontract forms NSC1-4, DOM1, TNS 1 and 2.  Collateral warranties then came into their own. How many of us even now truly understand the complex interrelationship of rights, duties, powers and liabilities these create?

 

Together with the Minor Works Form and the Intermediate Forms, the Prime Cost Form and the Design & Build Form of contract, we were supposedly given a contract for all occasions. But how many times are you, like me, left wondering which contract is truly appropriate because in truth, given the circumstances you are faced with at the time, none of them really is.

Moreover, it was clearly felt by the drafters of those (now not so new) contracts that those involved in the administration of building contracts were not generally conducting their relationships in a contractually proper manner, so that a large part of the increased size of these contracts springs from the incorporation of a series of rules governing procedures and telling users how they should act in various circumstances.  Something likened to a good practice manual, which, we are told, they should always have been doing anyway. As a single example look at the heading governing clauses 35.3-9 of JCT98 ‘Procedure (my emphasis) for Nomination of a Sub-Contractor’.

So those of us longer in the tooth were being told that our lifelong practices were inadequate: we had to mend our ways and conform to the new procedures; these procedures were described as contractual and we were therefore obliged to conform to them.

 

Faced with these innovations is it any wonder that JCT80 was initially greeted with less than exuberance and that there has been considerable resistance to its use?

 

Does this new order lead to less litigation?  Not a bit of it. Just read the law reports.  Look also at the armada of contract consultants and legal advisers that have sprung up to handle the new work. Very convenient. Create a new order of things, disturbing the old satisfactory order; then introduce a new form of expert to tell us how we should be conducting our business.

That, oh long-in-the-tooth one, is why you are confused.

Let me now digress and tell you of a legal philosopher of the late 19th early 20th century called Eugen Ehrich. He sought to discover the origin of law in society. His thesis was called “Fundamental Principles of the Sociology of Law”. What he says, effectively, is that what matters in society is not the formal law (what he called ‘Norms of Decisions’) but how people actually conduct themselves (‘Norms of Conduct’). Law, he said, is formed by the norms of conduct and the formal law will eventually adapt itself to the way people act in society, which is the “living law”. This is shown for example in the extent that trade practices formed the basis for the development of mercantile law.

 

Now draw the analogy of the way the Standard Forms of Contract are being drafted. Admittedly this is private and not public law, but the principle is the same in accordance with Ehrich’s thesis. The new forms of contract should have been written to reflect the way those involved in the administration and carrying out of building contracts have habitually conducted themselves. What the JCT have tried to do is to create a new order of conduct which those involved in the industry should follow. To the extent that this new order is not followed, Ehrich would say this is bad law and should be adapted to conform to the living law, i.e. the norms of conduct.

 

But what are the norms of conduct actually practised within the building industry? I suspect they have changed little despite the advent of these new forms and these mandatory procedures. We all know how we proceed individually; but there is, to my knowledge, no common fund of information which provides a source of data on the common practices of the industry. Herein lies a source of research as yet untapped, for some enthusiastic student to explore.

Once that has been done and the results obtained, I suggest the authors, myself and a representative Employers’ body get together to produce a new form of building contract which reflects, rather than tries to reform, practices within the industry. It will also adjust the allocation of risks less to the detriment of the Employer.

This form will then become a best seller.  The student will earn a lucrative living on the lecture circuit, and I shall retire to sunnier climes. All of course on ―the  royalties on the sales which will continue forever. Arbitrators will be largely redundant

So who is going to volunteer?

 

Oh yes, and those long in the tooth will become less confused.

Those in favour please say aye.

 

Peter J Solari