Opinion - Legal Comment

by Peter Horne

 

Acceptance of contracts

In my son’s article in issue 49 (Electronic Acceptance), he appears to leave a possibility that acceptance by e-mail could take place when sent – analogous with the postal rule.  As I would disagree with such a contention, this led me to address the possible means of acceptance of contracts at the beginning of the third millennium.

 

The so called ‘postal rule’ only applies to the post (telegraph/telegram are on actual receipt) when it is reasonably anticipated that acceptance will be by post.  The general rule is that acceptance must be received; the postal rule is an anomaly.

 

The postal rule can be traced back to Adams - Lindsell in 1818 (when post was carried by horse and stagecoach – the universal ‘penny post’ was introduced in 1840). The reason for the rule is unclear, the favourite appears to be that the post office acts as agent for the parties – which cannot be so: the post office only receives the package, it has no knowledge of the contents. It is my opinion that the ‘postal rule’ will disappear, probably at the latest when the Royal Mail faces full competition.  As the rule does not appear to extend to commercial carriers, I suggest that it is incongruous that acceptance may depend on the carrier used. As it stands, if you send an acceptance by second class post on a Monday, it may not actually be received until Wednesday; but, due to the rule, it could have been ‘received’ on the Monday (at the moment of posting), whereas the same letter, hand-delivered on the Tuesday, would be received on the Tuesday!  A withdrawal on the Tuesday (before receipt of the hand delivery) would be effective if the acceptance was being delivered by hand but would not be effective if sent by post!

I consider that, in the near future, all modes of acceptance will be subject to the same rule – actual or presumed receipt.

 

In this respect, it may be worth considering the likely presumption of receipt (i.e. when actual receipt is not proven):

 

1.      First class post – two working days

2.      Second class post – three working days

3.      Postal methods which include a guaranteed delivery (including DX) – as guarantee

4.      Fax – at time of sending

5.      E-mail – Same (or next) working day dependent upon time of sending

 

This assumes that the mode selected has been ‘approved’ by the offeror either expressly in the offer (in which case the mode will be only as specified) or impliedly by reference either in the offer or (probably) in a covering letter.

 

Interesting observations

In case it has passed anyone’s notice, the Late Payment of Commercial Debts (Interest) Act applies to all commercial contracts entered into after 7 August 2002.  This Act has been the subject of several statutory instruments (SIs), gradually extending its scope and setting the rate of interest – currently 8% above base rate (i.e. 12%).  The Act and all of the SIs can be viewed and downloaded for free on the  Stationery Office web site:  http://www.legislation.hmso.gov.uk/

This should now resolve problems as to whether there is a power to award interest (e.g. adjudication under the Scheme for Construction Contracts). Any attempt to avoid the Act will be void unless there is a ‘substantial’ remedy available under the contract. We have yet to see what a ‘substantial’ remedy is. An added advantage of claiming interest under the Act is that a fixed sum of additional compensation is also available.

 

Apportionment of costs

The Arbitration Act (and other contractual rules) provide that ‘costs follow the event’?.  What is ‘the event’ is often argued at length by counsel at all levels. Various studies have indicated that arbitrators have a widely differing opinion as to the application of ‘the event’. The Arbrix Construction Group has carried out an in depth study which, hopefully, will become generally available in due course. My own suggestion (which is compatible with the study) is that we should apply the same methods of characterisation as we are currently using in adjudication to distinguish between disputes and issues.  The method and required skills are precisely the same but the result is not identical – a single dispute may include more than one event.

 

Evidence or new dispute?

Whether evidence which is adduced in support of a particular contention forms a new dispute, which is outside the adjudicator’s jurisdiction, or is admissible evidence is the latest and, possibly, the most controversial topic to arise.  In the latest case of Nuttall -v- Carter, a new programme was introduced during the adjudication – it had not been in existence prior to the notice of adjudication.  While this programme sought to prove the same length of extended time as previous applications, the reasons were not precisely the same. The court found that the programme had introduced a new dispute, which had not crystallised prior to commencement and was therefore outside the jurisdiction of the adjudicator. This is a matter which has arisen (although not subject to examination by the court) and will continue to arise. I suggest that this should be examined by looking at the issue, not the entire dispute. A matter which tends to prove the dispute may be inadmissible if it does not confine itself to the issue. For example, evidence that a delay was caused by late provision of information would be inadmissible if the original contention was that the delay was caused by additional work, even though for the same period of time. Of course, as adjudication is a matter of contract, the parties may agree otherwise (it has happened but don’t hold your breath)

 

Peter Horne