Procedural Directions – Reconciling the Act with the Pact!

Rod O’Driscoll

Consider, if you will, the following basic propositions:

 

1.      Section 1 of the Arbitration Act 1996, and its whole philosophy, is that the agreement of the Parties should be paramount.

2.      Arbitrations can only arise by agreement between the Parties and generally speaking, the agreements for Arbitration contain detailed procedural steps to be used during the course of the Arbitration.

3.      Even if they do not, they refer to rules of an Institute or other Organisation which are to be adopted as to procedural matters if an Arbitration arises.  The rules are agreed to apply to whatever dispute might arise out of the contract whether it be, for example, a discreet issue on the interpretation of some contractual clause, the ascertainment of loss and expense or some technical engineering dispute such as, for example, the manner of drawing and laying cables.

4.      By contract, the principal duty imposed on the Parties and the Arbitrator, and one of the proclaimed advantages of using Arbitration, is that the procedure should be tailored to the dispute to save time and money (see Section 33 of the Act).

5.      In a nutshell, it’s Section 1 (Autonomy) versus Section 33 (Statutory Mandation).

 

Question:  Are the principles of autonomy of the Parties on the one hand, and the duty imposed on the Parties by Section 33 of the Act reconcilable in circumstances where the directions agreed by the Parties, in the pre-Arbitration agreement, conflict with the duty imposed by Section 33?

 

Which obligation is to prevail? And what is the effect, if any, of Section 33 of the Act where the hands of the Parties and the Arbitrator are tied (unless both Parties agree otherwise) by possibly having to use (usually), an unnecessarily cumbersome set of procedural rules that the Parties have agreed to abide by prior to commencement of the contract.

 

There is no doubt that the procedural concepts in Arbitration, of versatility and flexibility, are of considerable importance. They give it the edge over Court resolution of disputes; yet the tendency is for the Parties to feel themselves bound by and to adhere strictly to cumbersome and detailed time constraints imposed by institutional pre-contract requirements. A huge amount of time and money is spent by many organisations drafting such rules. However, it surely has to be accepted that, no amount of drafting subtlety is going to be able to replace the discretion that both the Parties and the Arbitrator can use when the ―nature of the dispute has crystallised.

 

It is the Arbitrator’s duty to adopt procedures that are suitable to the circumstances of the particular case (Section 33).  It is for the Parties to co-operate (Section 40). The difficulty is, that it is impossible for the Arbitrator to carry out this duty where the agreed directions are not consistent with the Act, unless and until the Parties agree, either that he should have the authority to do so, or they agree to vary the original contractual directions. Nor can it be in the lap of one Party to determine such a variation of the agreement; both Parties have to agree.  There may be all sorts of political and other factors whereby one Party would wish, quite contrary to the Act, to adhere to some pre-contractual directions that would delay or involve heavier costs than might otherwise be employed.

 

How, therefore, can the problem of this divergence be overcome?

First, let us consider the options open to the Parties.  It seems they may have the following options.

 

1.      In their “pre-contract” agreements for Arbitration they could provide for the utilisation or employment of the agreed procedures to be subject to the provisions of the Act.  Unless such a provision is made, it is quite clear that the Parties original agreement and directions must prevail and notwithstanding Section 33.  The Act proclaims that the Parties’ wishes are paramount (Section 1) subject only to such safeguards as are necessary in the public interest.  Is this (Section 33), a safeguard which can be classified as being in the public interest?  Doubtful! The difficulty is compounded by the fact that Section 33 is mandatory; in other words it cannot be ousted by the agreement of the Parties (as many other provisions in the Act can).

2.      Secondly, of course, the Parties can agree, where a dispute arises, to vary their original agreement.  Frequently they will do so but it will often by the case that for economic or other reasons one Party may wish to prolong the outcome or “out-finance” the other.  However, if the Parties can agree to a variation or to allow the Arbitrators direction to prevail, the problem can be overcome.

3.      Alternatively, the Parties may agree to vary one or the other of the pre-ordained directions.  This, however would be merely tinkering with the problem.  Supposing the dispute was capable of being determined by the Arbitrator, by the making of a single inspection of the locus in quo (page, Lord Woolf, the Latin!).  What use then for the detailed requirements of pleadings, discovery, time constraints and hearings, which a Party might be able to insist upon?

 

Next, what, if anything can the Arbitrator do to overcome the problem?

 

1.      Can he make it a condition of his appointment, that the Parties do agree to abide by his directions and vary the original terms – a bold step, that!

2.      Can he extend or curtail the existing prescribed directions as to time without the Parties’ agreement.  There is normally a degree of flexibility within the pre-contract conditions to enable extensions of time, but not usually powers of curtailment to enable times to be foreshortened without Parties’ consent. Could he demand that a step which is provided for in the directions be omitted as being totally unnecessary?  Not, it is suggested, without the consent of both Parties.

 

In my humble opinion, it is not in the interests of Arbitration that the Parties should bind themselves to procedural conditions prior to the dispute having arisen.  Indeed, it often seems absurd to me that pre-contractual provisions require, in the absence of agreement between the Parties, that the appointment of the Arbitrator be made by a President of an Institute of one discipline or another which may be wholly inappropriate.  Why, for example, should the Parties be restricted to the appointment of an Arbitrator by the President, say, of The Royal Institution of Chartered Surveyors who will almost certainly have to appoint, from its panel, somebody from that discipline.  If the dispute involves solely a point of law, or maybe a point of electrical engineering, surely such a provision is hopelessly inappropriate.  The problem is that one simply cannot foresee the nature of the problems that might arise.

 

In conclusion, it seems to me, as a comparatively new legal entrant to the Arbitral process, that there is a real flaw in the Arbitration procedures here.  In this connection, although it might not be of the most common practical importance, it is a flaw which is surely, of such significance, that it should be addressed by better Gungadins than I!

 

Answers please, on a postcard, to our revered Editor.

 

Rod O’Driscoll