The essence of time for adjudicators
During the last few months there have been several
cases which show the importance of time in construction adjudication. Although
arising out of construction adjudication and time limits imposed by litigation,
the principles are of general application - if the rules are that something has
to be done within a particular time then, in the absence of a mechanism for
extension, failure to comply has dire consequences.
Firstly, and most controversial, is within the
judgment of HHJ Peter Coulson in Hart Investments ltd -v- Fidler &
Anor in which he decided that a delay of even one day in referral of the
dispute was fatal to the adjudication. While neither the judge nor counsel
could find any direct precedent, many adjudicators are sure that they can
recall this matter in a previous judgment but no-one has yet found it! The
requirement is that the dispute shall be referred not later than 7 days after
the notice of intention to refer and there is no provision for extension. The
attitude among adjudicators generally (but with some notable exceptions) has
been that a delay will (usually) only disadvantage the Referring party itself,
by giving an additional period of notice to the other party. Rejection of the
Referral, due to delay, would only cause more delay and cost by having to start
again. The sensible solution has always been to allow the late referral to
proceed. I am happy that I have not yet had to make that decision although I
have been representing a responding party in the situation.
In arriving at his decision, Judge Coulson had
referred to the judgments in Simons Construction -v- Aardvark
Developments and Ritchie Bros -v- David Philips Commercials, both of
which were in respect of the late delivery of the adjudicators Decision which
has a strict date with restricted rights of extension.
The other cases are in respect of the late
delivery of the Decision.
Aveat Heating Ltd -v- Jerram Falkus
Construction Ltd was under the GC/Works contract which contained the term
'The adjudicator's decision shall nevertheless be valid if issued after the
time allowed' but the court (HHJ Havery) decided that this did not comply
with the Construction Act, therefore the Scheme for Construction Contracts
applied.
The same judge came to the same conclusion in
Epping Electrical Co Ltd -v- Briggs & Forrester (Plumbing Services)
Ltd which was under CIC adjudication rules and which contained a similar
term to Aveat Heating.
HHJ Peter Coulson was again involved in Cubitt
Building & Interiors Ltd -v- Fleetglade Ltd in which the adjudicator,
on the day before his day for completion, informed the parties that his
Decision had been made but still needed to be checked and proofed and asked
whether the parties would be in a position to settle his invoice as he intended
to operate a lien. Judge Coulson listed four principles, the result of which is
that a Decision which is not reached within 28 days (or the extended period)
'is probably a nullity' and that the Decision may be communicated
outside that period provided that it is communicated forthwith. In that
case, the adjudicator had complied but there is a warning that the Decision
cannot be delayed, whether for the exercise of a lien or other and that the
adjudicator may have to provide evidence as to when the Decision was made. I am
glad to say that Judge Coulson has echoed my thoughts precisely except that I
have always added the warning that, if the Decision is late, the adjudicator
may lose entitlement to any fee whatever!
Peter Horne
Return to
Index |