Peter Barnes: JCT 2005 and 2006 Contracts:
What's New and What's Changed 23 January 2008
We welcomed Peter Barnes, a member of the East Anglia branch, who
gave us a lightning tour of the new JCT Contracts introduced in 2005 and 2006
(and still coming). He started by setting out the structure of the new issue,
with suites of multi-level contracts, most incorporating main contract,
sub-contract and even sub-sub-contract and each with consistent colour-coded
design. Contracts had been given a new layout, with clauses consistently
grouped into sections to make it easier to find relevant conditions. Whatever
the size and complexity of the new contract forms, there would be sections
covering, for instance, payment, control of the work and completion.
Peter set the new contracts in the context of
previous JCT standard forms, explaining that the principles and allocation of
risk had not changed.
For larger works designed and/or detailed by or on
behalf of the Employer, the Standard Form (now SB2005) remained the recommended
contract. As before, there are With Quantities, Without Quantities and With
Approximate Quantities versions, but no separate Local Authorities' editions.
Each one has a standard 9 sections and 7 schedules. Optional provisions for
Contractor design of parts of the Works and for sectional completion are built
into the standard contract wording rather than requiring a separate supplement
with its confusing list of clause amendments. In Peter's view the dreaded
political correctness had crept in here just as in many other parts of
contemporary life. Now we must get used to Adjustment of the Completion Date
instead of extensions of time (the latter consigned to oblivion as it does not
sit easily with the new provision for an earlier completion date following a
Schedule 2 Quotation). Default retention is now 3% and there is an alternative
provision for a Retention Bond.
For works designed by the Contractor to
requirements prepared by or for the Employer and requiring detailed contract
provisions, DB2005 replaces WCD98. The contract conditions will be administered
by the Employer's Agent. In the payment provisions in this form, the Employer
must now pay 'the amount due' (previously 'the amount applied for' could become
the amount due). There's also a new up-to-the-minute Design Submission
Procedure with 'A', 'B' and 'C' status - where have I seen that before? It's
also been spelt out that the Contractor's Design liability is the same as that
of an experienced designer of the relevant discipline - goodbye to 'fitness for
purpose'.
The Intermediate Contract had now become IC2005,
with ICD2005 where parts (not the whole) are to be designed by the Contractor.
Both forms are suitable for works of simple content with no complex services
requiring more contract provisions than in the Minor Works form. Provisions
remain for named specialists. As with SBC2005, there are 'standard' options for
sectional completion.
The Minor Works suite has a standard form (MW2005)
and a design-and-build variant (MWD2005) which is suitable for contractor
design of a part, not the whole works. Both provide for the Contract
Administrator to administer the conditions.
In the spirit of the times, there is a partnering
contract. This is called 'Constructing Excellence' (CE), as that is what will
be achieved (obviously). As with all the best reforms, there is an Overriding
Principle, in this case of encouraging collaborative behaviour, just in case we
get bogged down in the everyday reality of laying one brick on top of another
whilst it's raining buckets. And of course the contract has to remind us that
we're part of a supply chain by being applicable at all levels - just don't get
labelled as the weakest link. At the top of the chain, there is a contract
between two parties (CE). Linked to this there is a Project Team Agreement
(multi-party, as a team needs more than two members to be effective). Risk is
shared by a pain/gain mechanism (similar to NEC), but as we're all excellent we
should only be in a win-win situation. To keep us all on the
straight-and-narrow, there is a Risk Register (what might go wrong) and Risk
Allocation Schedule (who's holding the baby), and design obligations are spelt
out. All this partnering and excellence is measured by KPI's (Key Performance
Indicators) so that we can have a table of numbers rather than trying to assess
Time, Cost and Quality (or even Commodity, Firmness and Delight, which
soundseven more touchy-feely but which are much the same). Finally, there are
Alternative Payment Provisions - no, not the sort guaranteed to appeal to
cash-strapped employers.
To ensure consumer choice, there is a whole range
of other contracts with initials and scope to gladden the heart of any Army
adjutant - MP (Major Project Construction Contract), CM/A (Construction
Management Appointment), PCC (Prime Cost Contract), MTC (Measured Term
Contract), FA (Framework Agreement), FA/N (Non-binding Framework Agreement) and
MC (Management Building Contract). As to scope, they'll cope with anything from
T5 or an Olympic stadium - oops, wrong family of contracts - to changing a tap
washer.
There is, as you would expect, guidance on how to
cope with all this supermarket-style array of goodies: the Practice Note
'Deciding on the appropriate JCT Contract' - gratis from the JCT website, and
additive-free (no initials and no colour-coding).
As widely reported the JCT has dropped its own
adjudication procedures and opted into the Scheme for Construction Contracts
(but with slight amendments - is anything sacred?).
At the beginning of Peter's talk, it seemed that
just listing the new contracts would take up the allotted time (there'll
probably soon be a diploma in JCT contracts and their identifying initials).
But Peter managed to pack a lot more in and by the end we felt we had a good
road map to guide us round the new world of the JCT.
Report (with additions) by Robin Orme
Return to
Index |