Case Law Update

Geoff Brewer 13 June 2000

Geoff Brewer is the Head of the consultancy practice Brewer Consulting, and is a frequent and well-known speaker at seminars and workshops on construction law. In recent years he has published over two hundred and fifty articles and papers on construction law and management issues. He has now been writing the weekly legal column for Contract Journal for the past four years, which is widely read and respected as a reliable and authoritative source for layers and construction professionals on construction law issues.

Geoff gave our Members an excellent explanation of a number of recent construction law cases covering both arbitration and adjudication and these are summarised below:

Defects Liability Provison

Pearce & High -v- Mr & Mrs Baxter

Court of Appeal 15 February 1999

The employer’s failure to comply with the notice requirements of defects liability provisions, whether by refusing to allow the contractor to carry out the repairs or by failing to give notice of the defects, limits the amount of damages which it is entitled to recover.

However, it should be noted that defects liability is in addition to common law rights and an employer has six years from practical completion to sue for breach of contract with regard to design faults or poor materials.

B/Q Rates

Henry Boot Construction -v- Alston Combined Cycles

CA 4 April 2000

In assessing the ‘reasonableness’ of a rate or price in contract bills for extended or varied work, regard may be had to whether the work is similar in character or conditions, but not to the intrinsic profitability or otherwise of the rate or price.

Total Costs Claims

How Engineering Services -v- Lindner Ceilings Floors Partitions

TCC 24 June 1999

An ascertainment of contractual loss and expense requires judgement, and may involve comparison of the total costs incurred with the costs which might have been incurred but for the delay and disruption.

Partnering Arrangements

Birse Construction Limited -v- St David Limited

TCC 12 February 1999

The existence of a partnering charter may influence decisions as to whether essential terms are present for the formation of a Contract and may further influence an arbitrator or court in determining whether performance has met the requirements of the Contract.

Extension of Time

Henry Boot Construction (UK) Limited -v- Malmaison Hotel (Manchester) Limited

TCC 18 October 1999

In assessing a claim for an extension of time, an architect is entitled to take into account matters which he considers delayed the works but which are not relevant events.

Adjudication

Macob Civil Engineering -v- Morrison Construction

TCC 12 February 1999

Adjudicator’s decisions are binding and enforceable pending final resolution of the dispute by arbitration or litigation.

Outwing Construction -v- H Randell & Son

TCC 15 March 1999

The court will be willing to accelerate the normal timescales for hearing an application for enforcement of an adjudicator’s decision.

Jurisdiction

Project Consultancy Group -v- The Trustees of the Gray Trust

TCC 16 July 1999

An adjudicator’s jurisdiction can be challenged where there is a failure to establish on clear evidence a relevant contract.

Palmers -v- ABB Power Construction

TCC 6 August 1999

On a challenge to jurisdiction the adjudicator should investigate and proceed accordingly, but he cannot rule upon his own jurisdiction.

Settlement

Lathom Construction -v- Brian & Ann Cross

TCC 29 October 1999

A settlement agreement will normally fall beyond the ambit of the Construction Act, and accordingly an adjudicator will not have jurisdiction to deal with disputes which flow from the agreement.

Determination

A&D Maintenance & Construction –v- Pagehurst Construction Services

TCC 23 June 1999

Even if the contract has been terminated, the matters referred to the adjudicator will remain disputes under the contract.

Construction Operations

Palmers -v- ABB Power Construction

TCC 6 August 1999

It does not automatically follow that a sub contract for ‘construction operations’? will be excluded from the Act if the main contract is for ‘excluded’ works.

Costs

John Cothliffe Limited -v- Allen Build (North West)

Liverpool CC 29 July 1999

Northern Developments (Cumbria) Limited -v- J&J Nichol

TCC 24 January 2000

An adjudicator may not award costs to a successful party unless the parties have agreed that he should do so.

Adjudicator’s Error

Bouygues UK Limited -v- Dahl-Jensen

TCC 17 November 1999

The court will enforce an adjudicator’s decision even where it is plainly based upon an error.

Correcting Slips

Bloor Construction -v- Bowmer & Kirkland

TCC 5 April 2000

A term may be implied into the adjudicator’s agreement whereby the parties give the adjudicator the power to correct manifest errors or omissions, or clarify or remove ambiguities in the decision. The power may be exercised on the initiative of the adjudicator or upon the application of one of the parties.

Set Off

VHE Construction plc -v- RBSTB Trust Company Limited

TCC 13 January 2000

Northern Developments (Cumbria) Limited -v- J&J Nichol

TCC 24 January 2000

A set off raised after the date of the referral will not prevent enforcement of the adjudicator’?s decision in full.

Dispute

Fastrack Contractors Limited -v- Morrison Construction Limited

TCC 4 January 2000

It is not always necessary for the full details of the quantification of a dispute to have been referred to the respondent prior to the adjudication.

Sherwood and Cason -v- Mackenzie

TCC 30 November 1999

The determination of a final account will generally be regarded as a different dispute to the determination of the last interim payment.

Concurrent Proceedings

Herschell Engineering Limited -v- Breen Property Limited

TCC 14 April 2000

Adjudication may be commenced ‘at any time’, but an adjudicator’s decision will be enforceable notwithstanding the prior commencement of legal proceedings concerning the same issues.