Dispute Resolution Boards      Peter Chapman - 15    May 2001

report by Roderick O’Driscoll

 

Peter Chapman, who is a Civil Engineer and a Barrister and a member of the South East Branch, talked to us about Dispute Resolution Boards (DRBs).  Dispute Resolution Boards (DRBs), Peter told us, were used commonly in construction and other areas such as concession contracts.

 

DRBs use a process for dispute resolution based on adjudication methods, but combined with an “on-site” knowledge, members of the Board periodically attending the site to become acquainted with the manner in which the contract was being executed.

 

Adjudication has changed the face of dispute resolution.  It is neither litigation nor arbitration.  It is not final and need not necessarily be enforceable.  It is a form of judicial process using the rules of natural justice.  It is inherent in their task that the Board use their own expert knowledge, and adjudicators can, of course, act inquisitorially.  There is a relationship with Engineers’ decisions, provided for by ICE or a FIDIC-style of contract, and much concern was expressed by Engineers when DRBs started as they felt it might be the beginning of their demise.  To a certain extend, Boards have replaced the Engineer, but Engineers do, of course, continue to be employed, and they fulfil a quite separate task under the contract from the DRBs.

 

DRBs are used for the larger value contracts.  Members are usually appointed one from each party, and a third is appointed by the other two. The difference between normal adjudication and Board adjudication is that they have a “job site” character and their task is not restricted only to when disputes arise.  Parties see them as a tool to be used and often do use them for advice on an informal basis.  Their presence reduces acrimony and disputes.  Parties temper their approach to each other because of the knowledge and the presence of the Board, and disputes are often resolved earlier than would otherwise be.  Cash flow is maintained, allowing parties to get on with the job of completing the project.

 

DRBs are now used in many countries.  The concept of DRBs is given support by the banks, by FIDIC and, to a certain extent, by the adjudication processes under the Regeneration Act of 1996.  Contractors have a habit of failing to learn from their experiences.  Partnering is all very well until you get involved in a dispute.  Conciliation and mediation is an excellent process, but there is often a need for a third party to actually make a determination.  Arbitration can cause high costs and delay.  Litigation is winning or losing; enquiry becomes inquisition, procedural issues loom high, and the process is lengthy and expensive.  By contrast, adjudication and DRB resolution are quick (although such speed does not permit time to check and re-check decisions made) and effective in maintaining the relationship between the parties.

 

A Board can consist of one adjudicator in smaller contracts, and the new FIDIC contract so provides.  Normally, however, there are three, and generally speaking they have different expertise. Members of a Board must sign statements of independence, and they must have the time and knowledge to deal with the matters as they arise.  Decisions always need to be supported by reasons to satisfy the losing party. The Board’s work is of an on-going nature, and they become part of the project process. So important is the constitution of the Board that financial support arrangements, for example from the World Bank, will usually be suspended until a Board is in place.

 

The number of site visits by a Board is typically three to four a year, sometimes more, sometimes less. During their visits their time is spent, not only in resolving any disputes, but also in giving advice and obtaining knowledge of what is actually happening. It is not unusual for a Board member to meet the parties separately to hear some background and for members of the Board to act quite informally as between the parties. It is only when a specific dispute is referred that procedures become ―formal and the jurisdiction to make determinations comes into effect. The informal part of their work, however, cannot be over-emphasised.  DRBs assist the parties to find a decision amongst themselves quickly and they can nip problems in the bud.

 

The average cost is 0.05% / 0.03% of the project cost, so that on a project costing £100,000,000 DRB expenses would typically be well under £100,000.  The cost is shared between the parties.  It is estimated that an arbitration dealing with similar disputes would cost three times as much as it costs to maintain the Board.

 

Formal proceedings before the Board commence by a reference. The Board will then convene on site for a hearing when necessary.  The parties set out their case on one or two sheets of paper, stating their position. When there is a hearing it will almost invariably be without lawyers, and be presented by engineers. There is no wrangling on procedure. The Board dictates the manner of proceedings, frequenting acting inquisitorially, and often requiring adjournments for further information. DRB hearings take on average one or two days, rarely more. After the hearing, the Board like to get their decision out as quickly as possible with their reasons and try to do this within two weeks at the most. Most decisions are resolved by a majority unless the contract provides otherwise.

 

In addition to their determinations, the parties use the Board for advising and giving opinions on a wide range of matters.  It is a fast-track system and meets and deals with problems head on.  It works because all parties co-operate.  The objects of both parties are the same, ie to see a completion within a specified time and to pay a proper and fair remuneration. Disputes arise after the contract has started because of variations and unforeseen matters.  Boards can resolve these things at an early stage.  Without a Board, a dispute remains unresolved and becomes a cancer. It then spreads infection and dissatisfaction between the parties, leading to further disputes.

 

The Board can be as flexible as the parties require. They can give binding determinations or recommendations. By requiring the provision of a DRB in their contracts, employers immediately show they intend to act fairly. The system is now wholly supported internationally. 

 

Though there has been some resistance to the system, experience shows that the parties increasingly appreciate its advantages. For example, both the employers and the contractors involved in the Hong Kong Airport project had been against a Board-type system when the contract started, but now that it is completed, they regret that the services of the Board were not used more frequently.

 

After the talk Peter dealt with a number of questions from the floor.

 

This talk must surely have been one of the most useful the Branch have had in recent months, covering as it did, aspects of alternative dispute resolution which are not frequently referred to. Our thanks to Peter for his excellent talk and for standing in at such short notice.