Delay and disruption - the contracting parties points of view

Anthony F Caletka and Dr John Keane  11 June 2002

Reported by Roy Sutcliffe

 

A well attended meeting at the Reigate Manor Hotel assembled to hear two topical speakers give an address on a topical subject. Thanks to the wide-ranging brief given to the speakers by our Chairman, the address covered a great deal of ground and was supported in detail by an ‘Acrobat’ presentation. It would be impossible in the space available to me to report in detail, and the following is little more than a list of headings. Readers who wish to explore the subject in more depth may take advantage of the very informative web site at http://www.keane-associates.com/.  It is also possible to obtain the ‘Acrobat’ pdf files. mailto:afc@keane-associates.com

Anthony Caletka and John Keane are respectively Managing Director and Director of Keane Associates, whose assignments include many major projects in various sectors of the construction industry.  Their fields of expertise include project management, CPM planning, forensic delay analysis, litigation support and due diligence auditing. Their address to the meeting was given in the following sections.

 

Delay Identification/Measurement.     Dr Keane discussed planning con-siderations, both pro-active and forensic, and drew attention to the development of these techniques from a rather theoretical paper exercise in the 1980's to the more practical computer-dependent procedure of today. Various delay analysis techniques are available including those with esoteric titles such as ‘impacted as-planned’ and ‘collapsed as-built’.

 

Contract and Case Law.  Dr Keane reminded us of the purposes of extension-of-time clauses, which he said were (a) to retain a defined time for completion, (b) to retain the Employer’s right to liquidated and ascertained damages, and (c) to give the Contractor relief from the strict duty to complete on time when delay was caused by neutral events. He went on to discuss the question of whether a notice of delay by the Contractor is a condition precedent to the award of an extension of time.  He referred to LB Merton -v- Stanley Hugh Leach (1985) in which it was held that it was not, but he also drew attention to the Australian case of Turner -v- Austotel (1994) in which it was held that a party to a contract cannot rely on the preventing conduct of the other party where it failed to exercise a right which would have negated the effect of that preventing conduct. Dr Keane touched on the liability of certifiers (of extensions of time) quoting the memorable phrase ‘incompetent best’ from Lubenham Fidelities.  The case of John Barker Construction -v- London Portman Hotel (1996) showed that failure to act fairly can lead to invalidation. A number of other relevant case were listed on the ‘Acrobat’ presentation.

 

SCL EOT Protocol   At this point Mr Caletka continued the presentation.  He had been very much involved in the development of the Extension of Time Protocol of the Society of Construction Law and was able to describe its evolution in some detail. So far more than 5,000 web-site visitors have visited the SCL web site and over 6,000 copies have been issued or downloaded. (Price GBP 7.50) The Protocol is not promoted as a universal panacea but there is no doubt that the wide interest in it has raised awareness of programming and extension of time issues. Its main objectives are to reduce the scope for disputes, particularly by resolving controversial contract administration and legal issues and to explain best practice techniques.

 

‘Burning Issues’.  Mr Caletka identified the three burning issues in the programming/delay analysis world as (a) ownership of float, (b) concurrent delay, and (c) right to early completion.  He amplified these points and then considered how the Protocol dealt with them.  Much of this was illustrated on the screen by examples of programmes, which can be found on the ‘Acrobat’ pdf files.  Mr Caletka did not hide from us that concerns remain about the implementation of the Protocol with regard to these issues and also from basically practical aspects of cost of implementation, shortage of skills, need for redrafting of contracts and a short-term risk of increasing areas of dispute.

 

Role of the Expert Witness 

In conclusion the role of the expert planner in disputes was explained. The case was made for the availability of a practitioner with a wide knowledge of current practice and skilled in, for example, CPM software and calculating extension of time on live projects.  The independence of the expert’s view on the pleaded case was established, but the expert’s role in presenting his findings and convincingly giving evidence drew some discussion from the floor.

Finally a vote of thanks by Chairman Derek Ross for a very thoughtful, informative and well presented address was approved with acclaim.