OPINION - LEGAL COMMENT - WHAT DISPUTE? - PETER HORNE
The top of the pops in adjudication cases during the first part of
this year has been determining the precise dispute (if any) which has been referred.
I have picked this topic as, once again, the principles may also refer to
arbitration.
The major relevant difference between these two
methods of dispute resolution is that the programme for arbitration is flexible
while adjudication under the Act has a very restricted timescale of 28 days,
only extendable with the agreement of the referring party. The advantageous flexibility in arbitration
has traditionally led to an agreed extension of jurisdiction to encompass all
disputes, even if arising after commencement of the reference.
Of course, adjudication
following the Construction Act has always required a fully crystallised
dispute; uncertainty only existed as to the boundary between evidence in
support of the existing dispute and the initiation of a new dispute. Recent judgments have indicated that the
courts may well consider any new approach as being a different dispute, outside
the scope of the original notice.
The Arbitration Act
1996 is very uncertain. Section 1 refers only to disputes?, which requires a
rejected (expressly or impliedly) claim. However, s.34(2)(c) makes reference to
statements of claim, rather than submission of the dispute.
I suggest that there must be a
crystallised dispute in existence before any method of dispute resolution can
be commenced. To do otherwise is folly there is nothing for the tribunal to
decide and it is clearly un-economic to identify the dispute while proceedings
are taking place (although common practice). In an adjudication to which the
provisions of the Construction Act refer, the crystallised dispute, as set out
in the notice, defines the jurisdiction of the adjudicator (see later for
recent judgments). However, my interpretation of the Arbitration Act is that,
save for any provision in the arbitration agreement itself, while it is
necessary to have a crystallised dispute in existence before commencement of
arbitration proceedings, the Claimant can then submit a claim which, although
within the general confines of the dispute, may include matters which have not
earlier been put to the Respondent. However, this is by no means certain, and
there may be a possible jurisdictional challenge to such a claim.
This interpretation is outside
my previous understanding of arbitration (in which the submission of further
disputes would require agreement of the parties) and, I submit, is illogical
and cannot have been the intention of Parliament.
I suggest that arbitrators
would be well advised to examine the adjudication cases and be prepared to
refuse jurisdiction in such circumstances if the Respondent submits that this
is not the dispute which was the subject of the arbitration notice. Of course,
the parties would be at liberty to re-define the dispute, but it may be proper
for the Claimant to be penalised in respect of any wasted costs
The first relevant case in
adjudication was Fastrack Contractors Ltd -v- Morrison
Construction Ltd (4 January 2000),
in which it was clear that, without specific agreement between the
parties and under adjudication rules which only talked of a dispute, the
adjudicator would only have jurisdiction to consider a single dispute. This
relates, in arbitration, to joinder. A single dispute may have many elements
but must have crystallised: A dispute can only arise once the subject matter
of the claim, issue or other matter has been brought to the attention of the
opposing party and that party has had an opportunity of considering and
admitting, modifying or rejecting the claim or assertion (Fastrack judgment
para 27).
In Chamberlain
Carpentry & Joinery Ltd -v- Alfred McAlpine Construction Ltd
further clarification was given in that ten separate issues were characterised
as a single dispute as to how much should be paid by McAlpine. I believe the
key is to identify the characterisation of the dispute individual issues
which are encompassed by that characterisation will be within the dispute
provided that each issue has crystallised.
While there has never been any
doubt that the dispute had to be fully crystallised before commencement, there
had been debate as to where the line was drawn between production of evidence
and the formation of a new dispute. Most readers who are involved with
construction disputes will recognise the common situation of preparing
additional programmes to demonstrate the cause of extended time. In Edmund Nuttall Ltd
-v- RG Carter Ltd (21 March 2001) judge Richard
Seymour decided that the production of a programme which had been prepared
specifically for the adjudication was a new claim which Carter had not seen
before it was annexed to the Referral Notice, formed a new dispute and was
therefore outside the adjudicators jurisdiction.
Peter Horne