Independent and Fair Decision Making
Isn't it about time that the architect was taken
out of the role of independent certifier? This continues to be a rich vein for
dispute however it seems to be an area where quick and easy action could be
taken to remedy the situation.
The architect's obligations essentially cover two
aspects; design of the works and the administration of the contract once works
commence on site. Within this latter role he must act as both the employer's
agent, acting in the best interests of the employer, and also as independent
certifier when certifying matters such as the value of the works or when
completion has been achieved.
The case of Sutcliffe v Thackrah clarified the
role of the certifier;
"The building owner and the contractor make
their contract on the understanding that in all such matters the architect will
act in a fair and unbiased manner and it must therefore be implicit in the
owner's contract with the architect that he shall not only exercise due care
and skill but also reach such decisions fairly, holding the balance between his
client and the contractor."
The position at common law is also reflected
within many of the major forms of contract such as JCT and ICE, however the
situation is an obvious source of dispute.
I have come across a number of instances where the
judgement of the architect has been called into question. In refurbishment
projects for example, I have frequently heard the argument that the contractor
should have known that there would be changes and therefore have allowed for a
certain level of change within his contract programme.
Another example concerned a contractor's apparent
failure to vet an architect's design and not pick up that the levels for
installing a complex roof guttering arrangement were not correct. Apparently
the contractor, who did not have any design responsibility, should have carried
out a full check and review of the design information prior to carrying out the
installation.
Further difficulties exist where the architect is
the source of delays in the provision of design information during the
construction phase. I have come across the situation where a whole floor was
missed from the design included in the tender documents. The error was only
discovered during an on site walkabout once the contractor arrived on site!
This had considerable ramifications on the design of the project affecting
amongst other things the location of room layouts, services, and lift
installations.
From a contractor's perspective it is not just
that a new design has to be issued (although that is bad enough!), it is the
subsequent timing of the issue of the revised design information that affects
his whole construction programme. What can typically happen is that the design
changes are issued piecemeal due to the pressure to reduce delay and get the
contractor progressing the works. However this prevents him from working in an
effective, logical and cost effective sequence. By the time the majority of the
design is received the Contractor has multiple trades on site working in what
has now become an overcrowded and congested site, working from hand to mouth on
scraps of design information. In such circumstances will the architect reach
his decisions fairly? On past performance it may be unlikely. There can be much
muddying of the waters, where the usual arguments come to the fore to avoid
issuing an extension of time or paying additional costs; the contractor was
behind programme and not ready for the design information, he failed to
mitigate the delays, he failed to effectively plan and sequence his works, he
failed to work efficiently.
In such circumstances it is hardly surprising that
the architect's duty to be independent is not top of his list of
considerations. More important is saving face, a client relationship and his
professional indemnity.
I am also aware of architects who are unhappy with
the situation and the undue pressure it can put on them. Even when an architect
is acting fairly and reasonably, the relationship he has with his paymaster may
still cause the contractor to question his judgement. Disputes have been known
to arise simply because of a perceived bias.
Why not take this whole area of potential conflict
out of the arena? Utilising a truly independent party to carry out the
certification obligations would not be difficult to introduce and would
immediately get rid of any perceived bias or self protection that is inherent
in the current situation. Parties would be far more willing to accept an
independent award, as has been shown when an Adjudicator makes his decision. It
would not necessarily cost any more, possibly being paid jointly by the
Employer and Contractor. Whatever arrangement is eventually arrived at it
surely must be a better arrangement than that which has existed for too long
and caused far too many disputes.
Jonathan Bowcott MBM Consulting, 20 April
2008
Return to
Index |